E20-895 · Question #61

Refer to Scenario 2. An EMC Avamar backup administrator has asked for a plan that allows all servers to complete initial backups over the next two nights. Which initial backup plan meets all…

The correct answer is A. Initiate file server backups first, database server backups next with multiple RMAN scripts, and then all. See the full explanation below for the reasoning.

Question

Refer to Scenario 2. An EMC Avamar backup administrator has asked for a plan that allows all servers to complete initial backups over the next two nights. Which initial backup plan meets all customer constraints and accommodates average Avamar data scan rates?

Exhibit

E20-895 question #61 exhibit

Options

  • AInitiate file server backups first, database server backups next with multiple RMAN scripts, and then all
  • BInitiate all backups at the start of the Saturday backup window; database server backups need the --parallel
  • CInitiate file server backups first followed by database servers next
  • DInitiate database server backups on Saturday and file server backups on Sunday

How the community answered

(28 responses)
  • A
    75% (21)
  • B
    4% (1)
  • C
    14% (4)
  • D
    7% (2)