An EMC Avamar customer has an IBM DB2 server with multiple instances; i.e., A, B, and C. - Instance A = 150 GB - Instance B = 300 GB - Instance C = 75 GB The customer has installed the Avamar DB2…

The correct answer is A. Migrate Instances B and C to two new DB2 servers. See the full explanation below for the reasoning.

Question

An EMC Avamar customer has an IBM DB2 server with multiple instances; i.e., A, B, and C.

  • Instance A = 150 GB
  • Instance B = 300 GB
  • Instance C = 75 GB

The customer has installed the Avamar DB2 client plug-in on this host and has configured an online backup schedule for each instance. Which additional step is required prior to starting the schedules for each instance?

Options

  • AMigrate Instances B and C to two new DB2 servers
  • BRun db2 update db cfg for <DATABASE-NAME> using LOGRETAIN ON for each instance
  • CCreate a file system backup schedule to include the archive logs for each instance
  • DModify the schedules for each instance to ensure they do not run simultaneously