An EMC Avamar customer has an IBM DB2 server with multiple instances; i.e., A, B, and C. - Instance A = 150 GB - Instance B = 300 GB - Instance C = 75 GB The customer has installed the Avamar DB2…
The correct answer is A. Migrate Instances B and C to two new DB2 servers. See the full explanation below for the reasoning.
Question
An EMC Avamar customer has an IBM DB2 server with multiple instances; i.e., A, B, and C.
- Instance A = 150 GB
- Instance B = 300 GB
- Instance C = 75 GB
The customer has installed the Avamar DB2 client plug-in on this host and has configured an online backup schedule for each instance. Which additional step is required prior to starting the schedules for each instance?
Options
- AMigrate Instances B and C to two new DB2 servers
- BRun db2 update db cfg for <DATABASE-NAME> using LOGRETAIN ON for each instance
- CCreate a file system backup schedule to include the archive logs for each instance
- DModify the schedules for each instance to ensure they do not run simultaneously
How the community answered
(20 responses)- A85% (17)
- C10% (2)
- D5% (1)