Dell-EMC
E20-818 · Question #129
An SRDF/Star solution has been proposed. The customer is slow to accept the solution because they are concerned about the reliability of the RDF daemon. How would you address the customer's concern?
The correct answer is A. RDF daemons will be deployed on multiple management stations at the workload site. The RDF. EMC E20-818 Exam
VNX Concepts and Architecture
Question
An SRDF/Star solution has been proposed. The customer is slow to accept the solution because they are concerned about the reliability of the RDF daemon. How would you address the customer's concern?
Options
- ARDF daemons will be deployed on multiple management stations at the workload site. The RDF
- BRDF daemon process runs on the Symmetrix array and has built-in redundancy.
- CRDF daemon process runs on the Symmetrix array. If the workload site RDF daemon fails, the RDF
- DRDF daemons will be deployed on one management station at each of the three sites. If the workload
How the community answered
(40 responses)- A85% (34)
- B3% (1)
- C10% (4)
- D3% (1)
Explanation
EMC E20-818 Exam
Topics
#SRDF/Star#RDF daemon#redundancy#management station
Community Discussion
No community discussion yet for this question.