A customer has configured a job to have a high impact level. How will the job engine react to this action?

The correct answer is A. It will allocate additional resources to the job when it runs. See the full explanation below for the reasoning.

Question

A customer has configured a job to have a high impact level. How will the job engine react to this action?

Options

  • AIt will allocate additional resources to the job when it runs.
  • BIt will not pause the job for higher priority jobs.
  • CIt will preserve the impact level if node load levels are too high.
  • DIt will lower the priority level if node load levels are too high.

How the community answered

(24 responses)
  • A
    75% (18)
  • B
    4% (1)
  • C
    17% (4)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.

Full E20-655 Practice