E20-616 · Question #202
You have an upgrade bin and the procedure that was approved by the CCA review process approximately a week earlier. Keeping in mind that Symmetrix code status can change frequently, which step(s)…
The correct answer is D. Have the customer sign-off on a document (SAAR or similar documentation) that has a description. See the full explanation below for the reasoning.
Question
You have an upgrade bin and the procedure that was approved by the CCA review process approximately a week earlier. Keeping in mind that Symmetrix code status can change frequently, which step(s) should be taken to help ensure a successful upgrade?
Options
- ACheck Enginuity Status and explain the planned changes to the customer, using the change
- BConfirm the change plan with the customer and check new parts for compatibility
- CFollow procedures that were approved by the review process
- DHave the customer sign-off on a document (SAAR or similar documentation) that has a description
How the community answered
(28 responses)- A14% (4)
- B4% (1)
- C4% (1)
- D79% (22)