E20-616 · Question #202

You have an upgrade bin and the procedure that was approved by the CCA review process approximately a week earlier. Keeping in mind that Symmetrix code status can change frequently, which step(s)…

The correct answer is D. Have the customer sign-off on a document (SAAR or similar documentation) that has a description. See the full explanation below for the reasoning.

Question

You have an upgrade bin and the procedure that was approved by the CCA review process approximately a week earlier. Keeping in mind that Symmetrix code status can change frequently, which step(s) should be taken to help ensure a successful upgrade?

Options

  • ACheck Enginuity Status and explain the planned changes to the customer, using the change
  • BConfirm the change plan with the customer and check new parts for compatibility
  • CFollow procedures that were approved by the review process
  • DHave the customer sign-off on a document (SAAR or similar documentation) that has a description

How the community answered

(28 responses)
  • A
    14% (4)
  • B
    4% (1)
  • C
    4% (1)
  • D
    79% (22)