nerdexam
Dell-EMC

E20-598 · Question #34

On an EMC Avamar server, the maintenance schedule is enabled. If the server is over a certain capacity, when will the server automatically cancel backups that are running under the default…

The correct answer is A. At the start of the blackout window. See the full explanation below for the reasoning.

Question

On an EMC Avamar server, the maintenance schedule is enabled. If the server is over a certain capacity, when will the server automatically cancel backups that are running under the default configuration?

Options

  • AAt the start of the blackout window
  • BAt the start of the maintenance window
  • CAfter the first checkpoint in the blackout window
  • DAfter the backup has fully completed

How the community answered

(26 responses)
  • A
    77% (20)
  • B
    8% (2)
  • C
    12% (3)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.

Full E20-598 Practice