What is the last step in the hardware installation portion of an EMC Avamar multi-node deployment?

The correct answer is A. Connecting to the customer network. See the full explanation below for the reasoning.

Question

What is the last step in the hardware installation portion of an EMC Avamar multi-node deployment?

Options

  • AConnecting to the customer network
  • BCabling the nodes to the switch
  • CPowering on the nodes
  • DConfiguring the internal switches

How the community answered

(33 responses)
  • A
    79% (26)
  • B
    12% (4)
  • C
    6% (2)
  • D
    3% (1)