You are backing up a group of clients that have varying schedules. Using the EMC NetWorker Administration interface, you need to perform a full backup of all clients in that group. How would you…

The correct answer is A. Set an override level in the backup schedules to Full in the next date. See the full explanation below for the reasoning.

Question

You are backing up a group of clients that have varying schedules. Using the EMC NetWorker Administration interface, you need to perform a full backup of all clients in that group. How would you ensure that a full backup is performed for a client when it is backed up during the next save group execution?

Options

  • ASet an override level in the backup schedules to Full in the next date
  • BChange the group level to Override
  • CUncheck the Force incremental option in the group resource Advanced tab.
  • DCreate a staging resource called full and set the destination pool to full.

How the community answered

(29 responses)
  • A
    72% (21)
  • B
    10% (3)
  • C
    14% (4)
  • D
    3% (1)