In which order are the steps performend when creating an EMC NetWorker application-based snapshot?

The correct answer is A. 1. Freeze application. See the full explanation below for the reasoning.

Question

In which order are the steps performend when creating an EMC NetWorker application-based snapshot?

Options

  • A
    1. Freeze application
  • B
    1. Flush buffers
  • C
    1. Freeze application
  • D
    1. Commit writes

How the community answered

(24 responses)
  • A
    83% (20)
  • B
    8% (2)
  • C
    4% (1)
  • D
    4% (1)