An EMC Avamar customer is running a backup that is being written to a Data Domain system. The Data Domain cleaning schedule runs at 8 A.M. on Tuesday mornings. Avamar maintenance runs daily at 6…
The correct answer is A. At the next Data Domain file system cleaning. See the full explanation below for the reasoning.
Question
An EMC Avamar customer is running a backup that is being written to a Data Domain system. The Data Domain cleaning schedule runs at 8 A.M. on Tuesday mornings. Avamar maintenance runs daily at 6 A.M. A backup has completed successfully; however, it is no longer needed. The customer manually deletes the backup on Wednesday afternoon using the Avamar Administrator. When is the space reclaimed on the Data Domain system?
Options
- AAt the next Data Domain file system cleaning
- BImmediately on the Data Domain system
- CAt the next scheduled Avamar garbage collection
- DWhen manually deleted from the Data Domain system
How the community answered
(21 responses)- A71% (15)
- B5% (1)
- C14% (3)
- D10% (2)
Community Discussion