Which report can be used to determine the daily change rate for EMC Avamar clients?

The correct answer is A. DPN Summary. See the full explanation below for the reasoning.

Question

Which report can be used to determine the daily change rate for EMC Avamar clients?

Options

  • ADPN Summary
  • BServer
  • CGroup Status Summary
  • DCheckpoint Utilization

How the community answered

(23 responses)
  • A
    74% (17)
  • B
    17% (4)
  • C
    4% (1)
  • D
    4% (1)