nerdexam
Dell-EMC

E20-559 · Question #90

What is a valid hierarchical structure in the Isilon Job Engine v2.0?

The correct answer is A. Jobs contain phases. See the full explanation below for the reasoning.

Question

What is a valid hierarchical structure in the Isilon Job Engine v2.0?

Options

  • AJobs contain phases
  • BTasks contain phases
  • CTasks contain jobs
  • DItems contain tasks

How the community answered

(35 responses)
  • A
    83% (29)
  • B
    11% (4)
  • C
    3% (1)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full E20-559 Practice