Question
An Isilon customer has two 5-node clusters; one for production and one for disaster recovery (DR). The customer's workflows are replicated to the DR cluster through SyncIQ on individual schedules. They shut down their production cluster for a scheduled DR test, failed over to the DR cluster, and continue their DR testing. Assume both clusters have identical shares, exports, and user authentication. Additionally, assume the client applications have been stopped and the DNS re-pointed. Which SyncIQ Policy method should be used to continue production operations?
Options
- ARevert
- BInitiate Manual Failback
- CInitiate Automated Failback
- DNo change is needed