nerdexam
Dell-EMC

E20-555 · Question #260

What do you need to take into consideration when planning a job schedule?

The correct answer is A. Any three other jobs can run at the same time and they can run in conjunction with restripe or mark. See the full explanation below for the reasoning.

Question

What do you need to take into consideration when planning a job schedule?

Options

  • AAny three other jobs can run at the same time and they can run in conjunction with restripe or mark
  • BMultiple restripe category job phases and one-mark category job phase can run at the same time.
  • CUp to three jobs can run at the same time. Multiple restripe or mark job phases can safely and
  • DUp to three jobs can run at the same time. Multiple restripe or mark job phases cannot safely and

How the community answered

(28 responses)
  • A
    71% (20)
  • B
    7% (2)
  • C
    4% (1)
  • D
    18% (5)

Community Discussion

No community discussion yet for this question.

Full E20-555 Practice