nerdexam
Dell-EMC

E20-542 · Question #5

During a scheduled outage of the primary site (R1), a company is operating their production on their disaster recovery site (R2). After the outage, they need to move production back to the R1 site…

The correct answer is A. Failback. See the full explanation below for the reasoning.

Question

During a scheduled outage of the primary site (R1), a company is operating their production on their disaster recovery site (R2). After the outage, they need to move production back to the R1 site. Which SRDF action is required?

Options

  • AFailback
  • BRestore
  • CResume
  • DFailover

How the community answered

(22 responses)
  • A
    82% (18)
  • B
    5% (1)
  • C
    9% (2)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.

Full E20-542 Practice