You are in the process of sizing a new VMAX3 solution. One of the workloads will be replicated with TimeFinder SnapVX. Workload Details:

Capacity = 10000 GiB IOPS = 400 Change Rate = 25% Mounted Snaps = 2 Mounted Copy IOPS = 20 How many additional IOPS will the VMAX Sizer account for with this workload due to SnapVX?

Options

  • A20
  • B40
  • C50
  • D400

How the community answered

(37 responses)
  • A
    16% (6)
  • B
    73% (27)
  • C
    8% (3)