A host running PowerPath, attached to a CLARiiON, is migrated to a new switch connected to the same CLARiiON. What are two [2] actions required to complete the migration?
The correct answer is A. Set the initiator failover mode B. Add the new luns to the hosts existing RAID group. See the full explanation below for the reasoning.
Question
A host running PowerPath, attached to a CLARiiON, is migrated to a new switch connected to the same CLARiiON. What are two [2] actions required to complete the migration?
Options
- ASet the initiator failover mode
- BAdd the new luns to the hosts existing RAID group
- CSet the SP mixed mode from the storage system properties menu
- DSet the access control mode from the storage system properties menu.
How the community answered
(52 responses)- A77% (40)
- C15% (8)
- D8% (4)
Community Discussion