A customer has several hosts connected to a CLARiiON and is using PowerPath. A switch failure causes PowerPath to mark several paths as "Dead". Which action needs to be taken to restore the paths…
The correct answer is B. Nothing; the Dead paths will be restored automatically. See the full explanation below for the reasoning.
Question
A customer has several hosts connected to a CLARiiON and is using PowerPath. A switch failure causes PowerPath to mark several paths as "Dead". Which action needs to be taken to restore the paths after the switch is replaced?
Options
- AIn thePowerPath GUI, mark the Dead paths as "Live"
- BNothing; the Dead paths will be restored automatically
- CRestartPowerPath and run "powermt display" for verification
- DTrespass the LUNs back to the original SP
How the community answered
(34 responses)- A9% (3)
- B85% (29)
- C3% (1)
- D3% (1)