Dell-EMC
E20-522 · Question #26
Refer to the exhibit A company has a CLARiiON for disaster recovery that is ready to be decommissioned. The planned replacement is at a remote site instead of at a local site to satisfy business…
The correct answer is B. MirrorView/A over FCIP. See the full explanation below for the reasoning.
Question
Refer to the exhibit A company has a CLARiiON for disaster recovery that is ready to be decommissioned. The planned replacement is at a remote site instead of at a local site to satisfy business requirement. What should be used for the new disaster recovery replication? EMC E20-522 Exam
Exhibit
Options
- AMirrorView/S over FCIP
- BMirrorView/A over FCIP
- CMirrorView/S over iSCSI
- DMirrorView/A over iSCSI
How the community answered
(50 responses)- A6% (3)
- B84% (42)
- C2% (1)
- D8% (4)
Community Discussion
No community discussion yet for this question.