A "Promote" operation for a consistency group did not complete successfully. The consistency group now contains mixture of primary and secondary images. What is the status of the consistency group?
The correct answer is C. Out-of-sync. EMC E20-522 Exam
Design Symmetrix Business Continuity and Disaster Recovery Solutions
Question
A "Promote" operation for a consistency group did not complete successfully. The consistency group now contains mixture of primary and secondary images. What is the status of the consistency group?
Options
- AQuasi Consistent
- BIncomplete
- COut-of-sync
- DScrambled
How the community answered
(53 responses)- A6% (3)
- B9% (5)
- C83% (44)
- D2% (1)
Explanation
EMC E20-522 Exam