What happens when a primary SP fails during a synchronization operation of a Clone, assuming default parameter settings?

The correct answer is B. Peer SP will resume synchronization operation for the Clone. See the full explanation below for the reasoning.

Question

What happens when a primary SP fails during a synchronization operation of a Clone, assuming default parameter settings?

Options

  • AManual intervention is required to trespass Source and CloneLUN to restart synchronizing
  • BPeer SP will resume synchronization operation for the Clone
  • CClone synchronization operation will restart when failed SP is replaced
  • DClone state will be Out-of-Sync

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    79% (37)
  • C
    6% (3)
  • D
    13% (6)