After acquiring a company 300 hundred miles from their current office a customer has asked EMC to help architect a single-hop application recovery plan. After careful analysis of the workload and available bandwidth, SRDF/AR was selected as the solution. If the SRDF/AR cycle time is set to 60 minutes, what is the maximum potential data loss?
Options
- A1 hours of data
- B1.5 hours of data
- C2 hours of data
- D3 hours of data