E20-515 · Question #69

What is the status of the R1 and R2 devices after performing an SRDF split operation?

The correct answer is B. R1 Read/Write; R2 Read/Write. See the full explanation below for the reasoning.

Question

What is the status of the R1 and R2 devices after performing an SRDF split operation?

Options

  • AR1 and R2 Not Ready
  • BR1 Read/Write; R2 Read/Write
  • CR1 Write Disabled; R2 Read/Write
  • DR1 Read/Write; R2 Write Disabled

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    79% (33)
  • C
    2% (1)
  • D
    14% (6)