Which two TimeFinder/Clone actions are initiated by performing a symclone establish operation?

The correct answer is C. Create and terminate. See the full explanation below for the reasoning.

Question

Which two TimeFinder/Clone actions are initiated by performing a symclone establish operation?

Options

  • AActivate and restore
  • BCreate and activate
  • CCreate and terminate
  • DRecreate and terminate

How the community answered

(33 responses)
  • A
    18% (6)
  • B
    3% (1)
  • C
    73% (24)
  • D
    6% (2)