In a particular process, the Review Invoice activity has a different calendar than the one selected on the process. Which calendar will the system use to resolve timers created for the Review…

The correct answer is A. the calendar applied to the activity. See the full explanation below for the reasoning.

Question

In a particular process, the Review Invoice activity has a different calendar than the one selected on the process. Which calendar will the system use to resolve timers created for the Review Invoice activity?

Options

  • Athe calendar applied to the activity
  • Bthe default system calendar
  • Cthe calendar applied to the process
  • Dthe calendar with the earliest date

How the community answered

(17 responses)
  • A
    76% (13)
  • B
    12% (2)
  • C
    6% (1)
  • D
    6% (1)