When an automatic activity with a custom workflow method fails, which action does the system perform?

The correct answer is D. sends the task to the inbox of the method performer. See the full explanation below for the reasoning.

Question

When an automatic activity with a custom workflow method fails, which action does the system perform?

Options

  • Ainvokes the previous activity
  • Bsends a notification to the performer of the next manual activity
  • Csends a notification to the performer of the previous manual activity
  • Dsends the task to the inbox of the method performer