Question

How should an application developer change values in the transition conditions for running process instances without uninstalling the process?

Options

  • Aby updating activity instances using UPDATE...OBJECTS DQL
  • Bby defining the transition using process parameters and setting the value during execution
  • Cby basing the transition on a structured data type and modifying the XML
  • Dby changing the value in the Transition tab of Process Builder and versioning the process