After a Task Form is associated with a manual activity within a process template, where else can that Task Form be used?
The correct answer is B. for any activity only within the original process. See the full explanation below for the reasoning.
Question
After a Task Form is associated with a manual activity within a process template, where else can that Task Form be used?
Options
- Afor any activity that has the same activity name
- Bfor any activity only within the original process
- Cfor any activity within any process
- Dfor only the original activity and process
How the community answered
(41 responses)- A2% (1)
- B83% (34)
- C5% (2)
- D10% (4)