Once a process dashboard has been configured, what must be done to expose it in the TaskSpace interface?

The correct answer is D. Associate it with an application tab. See the full explanation below for the reasoning.

Question

Once a process dashboard has been configured, what must be done to expose it in the TaskSpace interface?

Options

  • AAssociate it with a configurable action.
  • BAssociate it with a form template.
  • CAssociate it with a process template.
  • DAssociate it with an application tab.

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    11% (4)
  • D
    80% (28)