nerdexam
Dell-EMC

E20-385 · Question #15

You are installing an EMC Data Domain system with two expansion shelves in a customer- provided rack. When cabling the controller to the shelves, where does the host port on the last shelf in the…

The correct answer is A. Expansion port of the upstream shelf. See the full explanation below for the reasoning.

Question

You are installing an EMC Data Domain system with two expansion shelves in a customer- provided rack. When cabling the controller to the shelves, where does the host port on the last shelf in the chain get connected?

Options

  • AExpansion port of the upstream shelf
  • BExpansion port of the controller
  • CLast port is left un-cabled
  • DHost port of the controller

How the community answered

(34 responses)
  • A
    85% (29)
  • B
    3% (1)
  • C
    3% (1)
  • D
    9% (3)

Community Discussion

No community discussion yet for this question.

Full E20-385 Practice