Question
A company with a DR site connected with a 2 Gbps FC link has three vRPAs at each site. They are experiencing High Load events, although the FC link is not fully utilized. What would be the best solution to get the FC link utilization up as high as possible while mitigating those events?
Options
- AReplace the vRPAs with physical RPAs and start using a Distributed Consistency Group
- BAdd two more vRPAs to the Primary site and divide the Consistency Group into four
- CDivide the Consistency Group into two segments and start using Distributed Consistency
- DAdd two RPAs to the Primary site as well as the secondary site
Unlock E20-377 to see the answer
You've previewed enough free E20-377 questions. Unlock E20-377 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.