nerdexam
Dell-EMC

E20-375 · Question #148

Which type of Consistency Group requires a primary and secondary production copy?

The correct answer is A. MetroPoint. See the full explanation below for the reasoning.

Question

Which type of Consistency Group requires a primary and secondary production copy?

Options

  • AMetroPoint
  • BSynchronous
  • CDistributed
  • DAsynchronous

How the community answered

(53 responses)
  • A
    77% (41)
  • B
    4% (2)
  • C
    11% (6)
  • D
    8% (4)

Community Discussion

No community discussion yet for this question.

Full E20-375 Practice