An Isilon customer has two 5-node clusters; one for production and one for disaster recovery (DR). The customer's workflows are replicated to the DR cluster through SyncIQ on individual schedules…
The correct answer is A. Revert the SyncIQ Policy. See the full explanation below for the reasoning.
Question
An Isilon customer has two 5-node clusters; one for production and one for disaster recovery (DR). The customer's workflows are replicated to the DR cluster through SyncIQ on individual schedules. They shutdowntheir production cluster for a scheduled DR test, failed over to the DR cluster, and continue their DR testing. Assume both clusters have identical shares, exports, and user authentication and that the client applicationshave been stopped and the DNS re-pointed. What is the correct method to continue production operations?
Options
- ARevert the SyncIQ Policy
- BInitiate Manual Failback of the SyncIQ Policy
- CInitiate Automated Failback of the SyncIQ Policy
- DNo change to the SyncIQ Policy
How the community answered
(65 responses)- A71% (46)
- B8% (5)
- C17% (11)
- D5% (3)
Community Discussion