While implementing a new Symmetrix solution, the customer requests that five new hosts be added to the project. This is outside the scope of the project. Which step needs to be taken?
The correct answer is C. Notify the project manager to create a change request. See the full explanation below for the reasoning.
Question
While implementing a new Symmetrix solution, the customer requests that five new hosts be added to the project. This is outside the scope of the project. Which step needs to be taken?
Options
- AAsk the account executive to modify the statement of work.
- BImplement the new hosts as requested by the customer
- CNotify the project manager to create a change request
- DNotify the solution architect to redesign the solution
How the community answered
(45 responses)- A9% (4)
- B4% (2)
- C73% (33)
- D13% (6)