Dell-EMC
E20-335 · Question #82
An SRDF failover has been executed during the testing phase of an implementation. What is the expected status of the R1 and R2 devices after performing SRDF failover operation?
The correct answer is C. R1 Read/Wnte, R2 Read/Wnte. See the full explanation below for the reasoning.
Question
An SRDF failover has been executed during the testing phase of an implementation. What is the expected status of the R1 and R2 devices after performing SRDF failover operation?
Options
- AR1 and R2 Not Ready
- BR1 Wnte Disabled; R2 Read/Wnte
- CR1 Read/Wnte, R2 Read/Wnte
- DR1 Read/Wnte. R2 Wnte Disabled
How the community answered
(32 responses)- A3% (1)
- B6% (2)
- C75% (24)
- D16% (5)
Community Discussion