After acquiring a company 300 hundred miles from their current office the customer has asked EMC to help to design a single hop application recovery plan after careful analysis of the work load and…

The correct answer is A. 2 hours of data. See the full explanation below for the reasoning.

Question

After acquiring a company 300 hundred miles from their current office the customer has asked EMC to help to design a single hop application recovery plan after careful analysis of the work load and available bandwidth, SRDF/AR was selected as the solution. If the SRDF/AR cycle time is set to 90 minutes, what is the maximum potential data loss?

Options

  • A2 hours of data
  • B1.5 hours of data
  • C4.5 hours of data
  • D3 hours of data

How the community answered

(26 responses)
  • A
    73% (19)
  • B
    8% (2)
  • C
    15% (4)
  • D
    4% (1)