After acquiring a company 300 hundred miles from their current office the customer has asked EMC to help to design a single hop application recovery plan after careful analysis of the work load and…
The correct answer is A. 2 hours of data. See the full explanation below for the reasoning.
Question
After acquiring a company 300 hundred miles from their current office the customer has asked EMC to help to design a single hop application recovery plan after careful analysis of the work load and available bandwidth, SRDF/AR was selected as the solution. If the SRDF/AR cycle time is set to 90 minutes, what is the maximum potential data loss?
Options
- A2 hours of data
- B1.5 hours of data
- C4.5 hours of data
- D3 hours of data
How the community answered
(26 responses)- A73% (19)
- B8% (2)
- C15% (4)
- D4% (1)