Refer to the Exhibit. Production work has been resumed on the R2 devices after an SRDF Failover operation. Where will the changes made to the R2 device be reflected in an SRDF Query?
The correct answer is A. 3. See the full explanation below for the reasoning.
Question
Refer to the Exhibit. Production work has been resumed on the R2 devices after an SRDF Failover operation. Where will the changes made to the R2 device be reflected in an SRDF Query?
Options
- A3
- B4
- C1
- D2
How the community answered
(32 responses)- A78% (25)
- B13% (4)
- C3% (1)
- D6% (2)