Dell-EMC
E20-335 · Question #157
How many cycle switches will need to occur after a switch from synchronous to asynchronous mode before the data is consistent?
The correct answer is A. 0. See the full explanation below for the reasoning.
Question
How many cycle switches will need to occur after a switch from synchronous to asynchronous mode before the data is consistent?
Options
- A0
- B1
- C2
- D3
How the community answered
(53 responses)- A75% (40)
- B8% (4)
- C4% (2)
- D13% (7)