A customer has Oracle 9i running on a Microsoft Windows server. They want to deploy hot backups because the database cannot be shut down. What is a design consideration for backups when using the…

The correct answer is B. Backups initiated through Avamar Administrator are always Full backups. See the full explanation below for the reasoning.

Question

A customer has Oracle 9i running on a Microsoft Windows server. They want to deploy hot backups because the database cannot be shut down. What is a design consideration for backups when using the Avamar plug-in for Oracle?

Options

  • AUse of exclude/include lists in a dataset is supported
  • BBackups initiated through Avamar Administrator are always Full backups
  • CFile system backup should include the entire root directory for each Oracle instance
  • DFull and incremental backups are initiated through Avamar Administrator

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    73% (16)
  • C
    14% (3)
  • D
    9% (2)