nerdexam
Dell-EMC

E20-324 · Question #98

When interviewing customer personnel, you learn of two sets of requirements: - The technical team has a specific set of requirements that they have to meet. - The manager has a financial requirement…

The correct answer is A. Let both teams know of the constraints and see if there can be a mutual resolution. See the full explanation below for the reasoning.

Question

When interviewing customer personnel, you learn of two sets of requirements:

  • The technical team has a specific set of requirements that they have

to meet.

  • The manager has a financial requirement that has to be met.

As you begin to design, it becomes clear that, in order to meet the technical goal, the financial requirement will be exceeded. What should you do?

Options

  • ALet both teams know of the constraints and see if there can be a mutual resolution.
  • BSince this is a technical project you should design to the technical team requirements.
  • CBecause the manager is paying for the equipment, limit the design to fit into the financial
  • DDesign to the technical requirement and then take enough storage out to meet the

How the community answered

(16 responses)
  • A
    81% (13)
  • C
    6% (1)
  • D
    13% (2)

Community Discussion

No community discussion yet for this question.

Full E20-324 Practice