Dell-EMC
E20-324 · Question #130
A colleague reports a customer forwarded over 100 host and switch outputs to be qualified for VNX connectivity. They are concerned about the amount of time needed to process all the outputs. How can…
The correct answer is A. Use Sahara. See the full explanation below for the reasoning.
Question
A colleague reports a customer forwarded over 100 host and switch outputs to be qualified for VNX connectivity. They are concerned about the amount of time needed to process all the outputs. How can your colleague reduce the amount of time needed to process all the outputs?
Options
- AUse Sahara.
- BZip the files and load them into E-Lab Advisor.
- CUse NSD-U.
- DZip the files and load them into E-Lab Navigator.
How the community answered
(26 responses)- A85% (22)
- B4% (1)
- C4% (1)
- D8% (2)
Community Discussion