A customer is planning to use MirrorView/A to replicate their production data to a remote VNX array. The network latency between the two sites can fluctuate. What do they have to consider when this…

The correct answer is A. A longer update cycle will cause more COFW delays on the primary LUN. See the full explanation below for the reasoning.

Question

A customer is planning to use MirrorView/A to replicate their production data to a remote VNX array. The network latency between the two sites can fluctuate. What do they have to consider when this happens?

Options

  • AA longer update cycle will cause more COFW delays on the primary LUN
  • BA longer update cycle will increase the RPO, but have no impact on the primary site
  • CThey will have to define a larger Write Intent Log LUN to buffer the data
  • DDefine smaller update chunks to prevent the increase of the RPO

How the community answered

(21 responses)
  • A
    86% (18)
  • B
    5% (1)
  • C
    10% (2)