nerdexam
Dell-EMC

E20-018 · Question #24

E20-018 Question #24: Real Exam Question with Answer & Explanation

The correct answer is D. Termination agreement. Training: Mod 5, Governance, Risk, and Compliance

Question

A customer is determining whether to divest resources into a third-party cloud solution. They are concerned about what will happen should they decide to migrate their data back in-house. Which contractual agreement defines this scenario?

Options

  • AService-level agreement
  • BEnd-user license agreement
  • CNon-binding user contract
  • DTermination agreement

Explanation

Training: Mod 5, Governance, Risk, and Compliance

Community Discussion

No community discussion yet for this question.

Full E20-018 Practice