E20-018 · Question #222

An organization plans to migrate a single application from a traditional, physical infrastructure to new servers. These servers are the first of several planned for their VDC. This will be the pilot…

The correct answer is A. A forklift approach, because they can keep the old systems running in parallel and they have the capacity. See the full explanation below for the reasoning.

Question

An organization plans to migrate a single application from a traditional, physical infrastructure to new servers. These servers are the first of several planned for their VDC. This will be the pilot application for the VDC migration to be completed over the next 5 years. The project is well funded and the VDC has more than enough capacity to support the pilot application. Which migration strategy will they most likely use and why?

Options

  • AA forklift approach, because they can keep the old systems running in parallel and they have the capacity
  • BA phased approach, because they can keep the old systems running in parallel and they have the
  • CA forklift approach, because this allows them to re-purpose the old servers and add those resources to the
  • DA phased approach, because this allows them to re-purpose the old servers and add those resources to

How the community answered

(27 responses)
  • A
    85% (23)
  • B
    4% (1)
  • C
    4% (1)
  • D
    7% (2)