A small organization plans to migrate a critical application from a traditional, physical infrastructure to the first servers in their VDC. This will be one of several applications the organization…
The correct answer is A. A phased approach, because they have planning assistance that may be cost sensitive. See the full explanation below for the reasoning.
Question
A small organization plans to migrate a critical application from a traditional, physical infrastructure to the first servers in their VDC. This will be one of several applications the organization plans to migrate over the next 2-3 years. As this is a new VDC implementation, they have not yet realized any of the benefits of a fully virtualized infrastructure. They have retained an experienced consulting service to help them build a detailed migration plan. Which migration strategy will they most likely use and why?
Options
- AA phased approach, because they have planning assistance that may be cost sensitive.
- BA forklift approach, because they have new servers available and can move small sections of the
- CA phased approach, because they can keep the existing systems online in parallel with the new systems.
- DA forklift approach, since it is less expensive than a phased approach and existing systems can be
How the community answered
(45 responses)- A73% (33)
- B7% (3)
- C4% (2)
- D16% (7)