Which data center management activity helps ensure business continuity by eliminating single points of failure?
The correct answer is A. Availability management. See the full explanation below for the reasoning.
Question
Which data center management activity helps ensure business continuity by eliminating single points of failure?
Options
- AAvailability management
- BPerformance management
- CCapacity management
How the community answered
(29 responses)- A79% (23)
- B7% (2)
- C14% (4)