E20-001 · Question #189
During DR planning in a two data center setup you determine that: The remote site B will hold a copy of data that is 5 minutes behind the production data at site A It will take two hours after an…
The correct answer is A. Five minutes. See the full explanation below for the reasoning.
Question
During DR planning in a two data center setup you determine that:
The remote site B will hold a copy of data that is 5 minutes behind the production data at site A It will take two hours after an outage at site A to decide to shift production to site B An additional 3 hours will be needed to power up the servers, bring up the network and redirect users so site B can become productive What is the Recover Point Objective (RPO) of this plan?
Options
- AFive minutes
- BTwo hours
- CThree hours
- DFive hours
How the community answered
(35 responses)- A80% (28)
- B11% (4)
- C6% (2)
- D3% (1)