Question
During DR planning in a two data center setup you determine that: The remote site B will hold a copy of data that is 5 minutes behind the production data at site A It will take two hours after an outage at site A to decide to shift production to site B An additional 3 hours will be needed to power up the servers, bring up the network and redirect users so site B can become productive What is the Recover Point Objective (RPO) of this plan?
Options
- AFive minutes
- BTwo hours
- CThree hours
- DFive hours
Unlock E20-001 to see the answer
You've previewed enough free E20-001 questions. Unlock E20-001 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.