The Recovery Point Objective (RPO) of a company is 2 hours. Which statement is true in the event of a disaster?

The correct answer is A. No more than 2 hours of production data can be lost. See the full explanation below for the reasoning.

Question

The Recovery Point Objective (RPO) of a company is 2 hours. Which statement is true in the event of a disaster?

Options

  • ANo more than 2 hours of production data can be lost
  • BNo more than 4 hours of production data can be lost
  • CTime to resume production operations must be no more than 2 hours
  • DTime to resume production operations must be no more than 4 hours

How the community answered

(13 responses)
  • A
    77% (10)
  • B
    8% (1)
  • D
    15% (2)