Dell-EMC
E10-110 · Question #86
Which task can a performer complete when a workflow contains a reject flow?
The correct answer is A. Return a package to a previous performer. See the full explanation below for the reasoning.
Question
Which task can a performer complete when a workflow contains a reject flow?
Options
- AReturn a package to a previous performer.
- BCommand the system to perform the activity on behalf of a user.
- CAdvance a package from an activity to the next activity in the normal workflow.
- DAllow the activity to be performed by a person or multiple people.
How the community answered
(55 responses)- A85% (47)
- B9% (5)
- C2% (1)
- D4% (2)
Community Discussion
No community discussion yet for this question.