A running workflow instance's automated activity has failed and another automatic activity needs to be triggered. How can the workflow be configured to anticipate failures of the automated activity?
The correct answer is A. Configure the automated activity with a fault handling activity. See the full explanation below for the reasoning.
Question
A running workflow instance's automated activity has failed and another automatic activity needs to be triggered. How can the workflow be configured to anticipate failures of the automated activity?
Options
- AConfigure the automated activity with a fault handling activity.
- BConfigure the automated activity to auto retry.
- CConfigure the automated activity with a reject flow.
- DConfigure the automated activity to continue execution.
How the community answered
(20 responses)- A70% (14)
- C10% (2)
- D20% (4)
Community Discussion
No community discussion yet for this question.